Current status of the major facilities
-
The open-pit coal mine
-
1
Pre-design phase
Licensing work completed
-
2
Designing
Design work completed
-
3
Expert appraisal
Positive conclusion from the State Environmental Review, Glavgosexpertiza received
-
4
Construction and installation stage
Development has started
-
5
Equipment procurement
Equipment procurement in progress
-
6
Deadline
Planned by the end of 2021
-
7
The facility has been commissioned
By the end of 2021
-
-
The refinery
-
1
Pre-design phase
Preparation of documentation completed
-
2
Designing
Design work completed
-
3
Expert appraisal
Positive conclusion from the State Environmental Review, Glavgosexpertiza received
-
4
Construction and installation stage
Start of construction
-
5
Equipment procurement
Equipment procurement in progress
-
6
Deadline
Planned by the end of 2024
-
7
The facility has been commissioned
By the end of 2024
-
-
Marine coal terminal
-
1
Pre-design phase
Preparation of documentation completed
-
2
Designing
Design work completed
-
3
Expert appraisal
Positive conclusion from the State Environmental Review, Glavgosexpertiza received
-
4
Construction and installation stage
Start of construction
-
5
Equipment procurement
Equipment procurement in progress
-
6
Deadline
Planned by the end of 2023
-
7
The facility has been commissioned
By the end of 2023
-
-
Motor road
-
1
Pre-design phase
Licensing work completed
-
2
Designing
Design work completed
-
3
Expert appraisal
Positive conclusion from the State Environmental Review, Glavgosexpertiza received
-
4
Construction and installation stage
Start of construction
-
5
Equipment procurement
Equipment procurement in progress
-
6
Deadline
Planned by the end of 2023
-
7
The facility has been commissioned
By the end of 2023
-